"Unsurpassed Experience in Solar PV and Energy Efficiency Measures"

Example of Energy Efficiency Measures(EEMs) Project 

ANDERSON UHSD
SPECTRUM ENERGY SUMMARY OF PROPOSED EEM’S PHASE 1 OF A MULTI-PHASE DISTRICT WIDE PROJECT

New Administration Building Chiller – Since the only campus building used regularly during the summer was the administration building, a new, 40-ton chiller at the 200 building that provides chilled water only to this building instead of operating the existing 200-ton main chiller. This allows the main chilled water system, including chiller, primary pump, condenser pump, and the cooling tower, to be shut down for two months of the summer. A second aspect of this EEM is to reduce pump energy by changing the campus distribution system to a variable flow system. Since the chiller is a constant-flow unit, this would required converting the existing pump system to a primary/secondary system. The EEM required the following work:
Item 1: New Chiller

Item 2: New chilled water pumping

Annual Savings $17,205

Item 3: Controls recommissioning

The district currently has all fan coils scheduled to operate on a fixed schedule. This schedule assumes the worst-case scenario for building morning warmup and allowing for after-hours work. The proposed EEM modifies the existing software to change the morning startup time based on optimal start logic. Optimal start logic would look at how long it actually takes to bring the rooms up to occupied setpoint temperature then adjust each day’s startup time based on the actual outside air temperature. It also modifies the fan scheduling to shut down the fans once school is out. The staff has to hit the “override” button at each room’s temperature sensor to operate the fan and heating/cooling for after-school hours.

Annual Savings $19,397

Item 4: Lighting-Campus Wide Program 

Project consists of partial change out of ballast/lamps in 1,933 fixtures in all buildings. Motion sensors were installed where appropriate and a Use Factor of .9 and used as a standard and .8 used for high occupancy and/or after-hours use buildings such as gymnasiums, performing arts and cafeteria buildings. To maintain light levels at existing levels delamping was ruled out as an option. Determination of extended hours facility use was from numerous meetings with district site personnel, district modernization and mechanical consultants and personal observations during day and night walk-thru’s of the facilities.

Annual Savings $12,162

Item 5: Photovoltaic Solar System

Project consists of the installation of a 245kw solar photovoltaic systems ground mounted.

Annual Savings $52,896

Item 6: West Valley High – Rate Savings Change

Project consists of a rate change from A-10 to A-6

Annual Savings $16,672

Total Annual Savings: $118,332

 

Copyright ©2010 Spectrum Energy Development, Inc.